Skip to the main content.
 


HEAR FROM OUR CUSTOMERS

Check out these real world examples of how Packet Power transformed our customers’ operations.

Read Case Studies

 


STAY UP-TO-DATE WITH OUR BLOG

Keep up with the latest innovations and trends in energy and environmental monitoring.

Read Our Blog

 


LOOKING FOR HELP?

Our technical support team is happy to assist.

Submit a Ticket

6 min read

The Fastest New Megawatt Might Already Be in Your Data Center

The Fastest New Megawatt Might Already Be in Your Data Center

Before you wait years for new utility power, ask a different question: Are you already using all of the power you have? 

Data centers are spending enormous time and capital looking for new power. But in some operating facilities, the constraint may be more complicated than the total amount of power available. There may also be limited visibility into where capacity exists, whether it is available at the required distribution point, and how much can be deployed without compromising redundancy, cooling or uptime.

Without granular monitoring, it's difficult to know where capacity exists, what's truly available, and what's being held back by uncertainty. In the right facility, one of the fastest ways to deploy additional compute may not be new infrastructure. It may be understanding and more effectively using the infrastructure already installed. 

Installed Capacity Usable Capacity

A 40 MW data center doesn't automatically have 40 MW available for new workloads. 

In reality, usable capacity can be limited by:

  • Feed Imbalance
  • Phase Imbalance
  • Local Panel, Busway, or Distribution Constraints
  • Cooling Limitations
  • Required  Redundancy and Failover Reserves
  • Capacity Allocated to Future or Discontinued Workloads
  • Incomplete Monitoring
  • Breaker and Equipment Ratings
  • Maintenance and Customer-SLA Requirements

This distinction between installed capacity and usable capacity is where many facilities leave opportunity on the table. Until operators can measure these conditions throughout the electrical hierarchy, available capacity remains an estimate rather than an engineering-validated operating resource.

26_07_27_ex.2

How Much Capacity Could Be Hiding?

Operators don't intentionally strand capacity. Capacity can become stranded because uncertainty is expensive. Without detailed operating data, engineering teams appropriately maintain safety margins to protect uptime. Some of those margins are required. Others may be based partly on estimates, incomplete measurement or operating assumptions that have not been continuously validated.

Consider an illustrative 40 MW facility.* If granular power visibility, balancing and site-specific engineering supported an increase from 50% to 60% average facility utilization, the facility could accommodate 4.0 MW of additional total facility load.

26_07_27_ex.1-3At a representative PUE of 1.44, that translates to approximately:

  • 2.78 MW of incremental IT or compute capacity
  • A 20% increase over the existing average IT load
  • No change to the facility's 40 MW nameplate capacity

*Important qualification: This is an illustrative opportunity scenario—not a forecast, savings guarantee or universal operating profile. It does not establish that every 40 MW facility can safely increase average utilization to 60%. Actual deployable capacity depends on measured peaks, redundancy, failover requirements, breaker and equipment ratings, cooling performance, maintenance conditions, workload reservations and local distribution constraints.

The Operating Questions That Matter

Better visibility doesn't create capacity. It reduces uncertainty about the capacity that's already there.

Granular power monitoring helps operators determine:

  • Where capacity exists
  • Whether it is available at the required distribution point
  • How load behaves over time, including peaks and variability
  • Where feeds, phases or circuits are imbalanced
  • Whether electrical and thermal capacity are aligned
  • How much capacity remains after additional compute is installed
  • Whether required redundancy and failover margins will be preserved
  • Which capacity reservations remain necessary and which may be obsolete

The objective is not simply to measure energy consumption. It is to produce the operating evidence required to determine what capacity is genuinely usable.

Visibility Creates Opportunity

Once usable capacity is identified, and approved for deployment, its value extends well beyond electrical engineering. Every month that additional compute can be deployed sooner has operational and financial implications that vary by business model.

The value of earlier capacity has three primary components:

  • Operating Value: What revenue, contribution or cost savings can the workload produce?

  • Time Value: How much economic output is delayed while the workload waits for power?

  • Capital Value: What infrastructure investment can be avoided or deferred? 

The correct economic lens depends on the operator and the workload.


Economic Lens Representative Value What is Measured
Enterprise or Hyperscale Workload Value Customer-Specific Revenue, Contribution Margin, Savings, or Strategic Acceleration
Wholesale Capacity Reference $6.5 Million Per Year Gross Rental Value at $196.25 per kW-month
Equivalent New-Build Capacity $31.4 Million Construction-Cost Equivalent at $11.3 Million per MW
AI Compute-Service Proxy $69.3 Million Per Year Gross Service-Value Proxy at 70% Utilization

*These are alternative ways of valuing the same illustrative capacity. They should not be added together, and none should be interpreted as profit, cash flow, guaranteed customer savings or enterprise value.


 Deploy Compute Sooner

When paired with site-specific engineering review and approval, granular operating evidence may allow new servers, AI infrastructure or other workloads to be deployed sooner—potentially before new utility power or major infrastructure upgrades become available. 

  Delay Capital Spending

Not every capacity challenge requires building more infrastructure. By making better use of the power already installed, organizations may be able to defer costly electrical upgrades, facility expansions, or new construction until they're truly needed. 

The benefit is not necessarily the permanent elimination of capital spending. It may be the financial and strategic value of delaying that spending while deploying productive compute sooner.

  Make Better Use of Existing Infrastructure

Limited visibility can cause an operating facility to appear constrained before every local opportunity has been evaluated. Granular power monitoring can help identify imbalances, lightly loaded distribution paths, localized constraints and obsolete reservations that may warrant engineering review. 

The objective is not to eliminate legitimate operating reserves. It is to separate capacity that must remain reserved from capacity that may be stranded because of imbalance, incomplete measurement or unnecessary uncertainty.

  Bring Revenue-Generating Workloads Online Faster

For colocation providers, cloud operators, and enterprise data centers, every month a new workload sits idle is a missed opportunity. Understanding where usable capacity exists allows organizations to provision new customers, applications, or AI infrastructure sooner—accelerating the value those workloads deliver.

For enterprise and hyperscale operators, the most important measure may not be rental income. It may be the contribution, operating savings, research output or strategic advantage created by making the underlying workload available sooner.


Why Time Matters

A megawatt made available inside an operating facility today may be economically more valuable than an equivalent megawatt that becomes available only after a lengthy construction or utility-interconnection process.

Capacity Available Sooner By Wholesale Capacity Reference AI Compute-Service
Proxy at 70% Utilization
3 Months $1.6 Million $17.3 Million
6 Months $3.3 Million $34.7 Million
12 Months $6.5 Million $69.3 Million
18 Months $9.8 Million $104 Million
24 Months $13.1 Million $138.7 Million

*The wholesale and AI figures are alternative gross-market proxies. They do not deduct servers, electricity, cooling, networking, storage, software, maintenance, support, financing, depreciation, facility expense, discounts, or idle and unavailable capacity.


Why Capacity Gets Stranded

  Feed Imbalance

Power may exist at the facility level but not where new equipment needs it.

   Phase Imbalance

One overloaded phase can prevent additional deployment even when overall capacity looks available.

  Cooling Constraints

Electrical capacity is only useful if thermal capacity is available too.

   Redundancy and Failover Requirements

Capacity must remain available to support equipment or power-path failures. This is a legitimate reserve, not stranded capacity. Any additional deployment must preserve the required operating model. 

   Reserved Capacity

Power may be allocated for to future customers, planned expansions or workloads that no longer require it. Monitoring and operational review can help determine which reservations remain necessary. Only obsolete or no-longer-required allocations should be considered candidate capacity.

   Limited Visibility

When operators can't see actual load behavior, peaks and variability, they may retain additional operating margin because the risk is uncertain. Better measurement may reduce that uncertainty. It does not eliminate risk or replace conservative engineering where it remains appropriate.

Five Steps to Unlock Your Existing Capacity

1. Establish the actual operating baseline.
Measure average and median demand, maximum observed demand, short-duration peaks, 95th- and 99th-percentile demand, peak frequency and duration, hourly and daily variation, feed imbalance, phase imbalance, allocated but unused capacity, and thermal conditions during high-load periods. The objective is to replace estimated loading with measured operating behavior.

2. Map the electrical hierarchy.
Evaluate capacity at the point where new compute will actually be installed:

  • Utility and Generator Feeds

  • Switchgear

  • UPS systems

  • PDUs and RPPs

  • Busways

  • Distribution Panels

  • Branch Circuits

  • Cabinets and Equipment Loads

A site may have power available in aggregate while a particular room, feed, busway or panel remains constrained.


3. Identify correctable constraints.
Monitoring can help engineering teams evaluate opportunities to:

  • Rebalance Redundant A and B Paths

  • Redistribute Load Between Panels or Busway Segments

  • Correct Phase Imbalance

  • Release Obsolete Capacity Reservations

  • Consolidate Lightly Loaded Equipment

  • Address Localized Cooling Limitations

  • Coordinate Electrical and Thermal Capacity More Effectively

  • Review Whether Operating Reserves Remain Appropriate for Measured Conditions

4. Establish an engineering-approved operating envelope.
Preserve:

  • Required Redundancy

  • Failover Capacity

  • Breaker and Equipment Ratings

  • Cooling Reserve

  • Maintenance Flexibility

  • Customer SLAs

  • Safety Standards

  • Internal Engineering Requirements

5. Add compute incrementally and validate continuously.
Add load in controlled stages while measuring:

  • Average Load,

  • New Peak Demand 

  • Feed Balance

  • Phase Balance

  • Thermal Conditions

  • Remaining Headroom

  • Alarm Events

  • Redundancy Performance

This converts capacity planning from a periodic estimate into a continuously validated operating process.

Good monitoring doesn't tell engineers what to do. It gives them the confidence to make better decisions with real operating data instead of assumptions. Monitoring informs the decision. It does not replace engineering judgement.

 

How Packet Power Helps

Packet Power provides granular power and environmental monitoring throughout the data center electrical hierarchy—from branch circuits and cabinets to panels, PDUs, busways and other distribution points. Our solutions are interoperable by design and use industry-standard protocols to integrate with existing DCIM, BMS and third-party platforms. This allows operators to collect the operating evidence needed to evaluate capacity without replacing the management systems they already use.

The objective is not simply better reporting. It is better operating intelligence: where capacity exists, whether it is available where needed, how load behaves over time and how much validated headroom remains as additional compute is deployed.

 

The Next Megawatt May Already Be There

As AI infrastructure grows and utility power becomes harder to secure, every available kilowatt matters. The organizations that move fastest won't necessarily be the ones that build first—they may be the ones that understand their existing infrastructure most precisely. Data center power monitoring doesn't create new electrical capacity. It helps operators:

  • Identify Where Candidate Capacity May Exist

  • Reduce Uncertainty Using Measured Operating Data

  • Preserve Required Redundancy and Operating Margins

  • Deploy Additional Compute Within an Engineering-Approved Envelope

  • Make Better Use of Every Megawatt They've Already Funded

The fastest new megawatt may not be a new megawatt at all. It may be existing capacity that measurement, balancing and engineering make usable sooner.

Methodology and Sources

This article summarizes an illustrative economic and operating model. The principal source inputs used in the full study include:

  • Facility-Size Benchmark: A dataset of 403 operating U.S. hyperscale data centers, with a 39.8 MW average and 35 MW median total facility electrical capacity
  • Utilization Assumption: Lawrence Berkeley National Laboratory's 50% average capacity-utilization planning assumption
  • PUE Assumption: Uptime Institute's reported 1.44 average PUE for facilities with power demand of 20 MW and above
  • Wholesale-Capacity Value: CBRE's H2 2025 North American wholesale asking-rent benchmark
  • AI Compute-Service Inputs: Published AWS EC2 Capacity Blocks pricing and NVIDIA DGX H100 system documentation
  • Construction-Cost Reference: JLL's 2026 global data center construction-cost forecast

The assumptions should be replaced with measured site-specific data before any operating or investment decision is made. Monitoring reduces uncertainty; it does not eliminate operational risk.

 

One Path to

1 min read

One Path to "Monitoring Nirvana"

We ran across a good article in the Data Center Journal written by Leon Adato entitled "Monitoring Nirvana" describing data center monitoring and who...

Read More
Volta Data Centres Nominated for DCS Awards

1 min read

Volta Data Centres Nominated for DCS Awards

We are pleased to learn that Volta Data Centres, a London-based co-location services provider, has been nominated for two 2016 DCS awards.

Read More
Volta Data Centres Uses Power – To Power Growth

1 min read

Volta Data Centres Uses Power – To Power Growth

Volta Data Centres, located in central London, has developed two innovative ways to use power as a point of differentiation to its prospective...

Read More